Skip to main content

Overview

Case Category
Request for Advice
Page last updated
24/03/2022
Commissioner (Panel Chair)
Dianne Leeson
Other Commissioners
Adrian Pilton, Ross Carter
Planning Officer
Dennis Lee, Olivia Hirst
Share this case
Case Status: Advice finalised
Referral received: 07/06/2018

Documents

Advice Report
Wallacia Crown Cemetry Development 120719 FINALsec
Media Statement
IPC_MediaStatement_WALLACIA CROWN CEMETERY
Letter to Sydney Western City Planning Panel
190712OUTJustin DoyleJRPP WallaciaRedacted
For further questions in relation to this matter please contact the Planning Panels Secretariat
Planning Panels Contact Details
190423 Wallacia cemetery
190322 Speakers Schedule
Meeting Notice Wallacia
IPC_Speaker registration form
190219 Site Inspection Notes Wallacia Cemetery
IPC DA Presentation Combined Varroville and Wallacia
IPC DA Presentation Landscape Design Wallacia
IPC Media Statement
150419 Email Infrastructure NSW to IPC_Redacted
190227 Letter IPC to DPE
190313 Letter DPE to IPC
190319 Letter Urbis to IPC
190321OUTUrbis re CCMT cemeteries
190412 Letter Penrith Council to IPC
190412 Letter Penrith Council to IPC Attachment Wallacia Timeline
190415 Email JA McGovern to IPC
190430INMillsOakleyCMCTCemeteries
190606INPeter OMearaCMCTRedacted
190607INPeter OMearaCMCT incl GSC
190607OUTP OMearaCMCTRedacted
CCNSW Submission to the Commission Varroville Wallacia DAs 11102018Redacted
CCNSWMetropolitanSydneyCemeteryCapacityReport
Cemetery Land Use Contribution to Environmental Heritage values by Carolyn Tallents August 2018
Commission email to CCNSW 19102018_Redacted
Commission email to Mr Darrell Bell 18122018_Redacted
Commission email to Penrith City Council 382018_Redacted
Commission email to Urbis 4102018_Redacted
Commission email to Wallacia Progress Association 2412019_Redacted
Commission email to Wallacia Progress Association 3102018_Redacted
Commission email to Wallacia Progress Association 6112018_Redacted
Commission letter to Department of Planning and Environment 182018
Commission letter to Department of Planning and Environment 382018
Department Response Letter 1112018
Email from Jeff Agius to the Commission 2312019_Redacted
Natural Resources Access Regulator Information 8112018_Redacted
Penrith City Council email to the Commission 12112018_Redacted
Penrith City Council letter to the Minister for Planning 672018_Redacted
Wallacia Progress Association email to the Commission 30112018_Redacted
Comments received by Penrith Council
1
10
100
101
102
103
104
105
106
107
108
109
11
110
111
112
113
114
115
116
117
118
119
12
120
121
122
123
124
125
126
127
128
13
14
15
16
17
18
19
2
20
21
22
23
24
25
26
27
28
29
3
30
31
32
33
34
35
36
37
38
39
4
40
41
42
43
44
45
46
47
48
49
5
50
51
52
53
54
55
56
57
58
59
6
60
61
62
63
64
65
66
67
68
69
7
70
71
72
73
74
75
76
77
78
79
8
80
81
82
83
84
85
86
87
88
89
9
90
91
92
93
94
95
96
97
98
Access Statement DA17 1092 Wallacia Memorial Park Cemetery
Acoustic Assessment DA17 1092 Wallacia Memorial Park Cemetery at 13 Park Road and 512 Mulgoa
AI 21 May 2018 Appendix D Traffic Impact Assessment Propo
AI 21 May 2018 Appendix F Civil Engineering Report Propos
AI 21 May 2018 Appendix G Stormwater Management Plan Prop
AI 21 May 2018 Appendix H Vegetation Management Plan Prop
AI 21 May 2018 Appendix I Tree Report Proposed Staged Con
AI 21 May 2018 Appendix J Public Health CMCT Response Let
AI 21 May 2018 Appendix K Acoustic Studio Letter Proposed
AI 21 May 2018 Appendix L Hydraulic Engineers Letter Ma
AI 21 May 2018 Proposed Staged Wallacia Memorial Park at 131
AI 21 May 2018 Appendix A Landscaping Plans Proposed Stag
AI 21 May 2018 Appendix B Civil Engineering Plans Propose
AI 21 May 2018 Appendix C WSUD Concept Plans Proposed Sta
Air Quality Impact Assessment DA17 1092 Wallacia Memorial Park Cemetery
Architectural Design Statement DA17 1092 Wallacia Memorial Park Cemetery
Building Code of Australia Compliance Statement DA17 1092 Wallacia Memorial Park Cemetery
Building Surveyor Referral Response of DA17 1092
Bushfire Protection Assessment DA17 1092 Wallacia Memorial Park Cemetery
Civil Engineering Services DA17 1092 Wallacia Memorial Park Cemetery
Clares Letter to Urbis Pty Limited regarding DA17 1092 identified key issues regarding Staged Con
Community Safety Officer Referral Response of DA17 1092
Contamination and Hazardous Material Assessment DA17 1092
DCP Compliance Assessment DA17 1092 Wallacia Memorial Park Cemetery
Dept Planning and Environment Respose
Electrical Infrastructure Report DA17 1092 Wallacia Memorial Park Cemetery at 13 Park Road and 512 M
Environmental 1st Biodiversity Referral Response of DA17 1092
Environmental Biodiversity Referral Response June 2018 of DA17 1092
Environmental Biodiversity Referral Response of DA17 1092
Environmental Environmental Management Referral Response June 2018 of DA17 1092
Environmental Environmental Management Referral Response of DA17 1092
Environmental Public Health Referral Response Dec 2017 of DA17 1092
Environmental Public Health Referral Response June 2018 of DA17 1092
Environmental Waterways Referral Response of DA17 1092
Environmentally Sustainable Design Strategies DA17 1092 Wallacia Memorial Park Cemetery at 13 Park R
External Plans DA17 1092 Wallacia Memorial Park Cemetery at 13 Park Road and 512 Mulgoa Road Wallaci
Flood Impact Assessment DA17 1092 Wallacia Memorial Park Cemetery
Flora and Fauna Assessment DA17 1092 Wallacia Memorial Park Cemetery
Geotechnical Groundwater and Salinity Report DA17 1092 Wallacia Memorial Park Cemetery
Heritage Impact Statement DA17 1092 Wallacia Memorial Park Cemetery at 13 Park Road and 512
Heritage Referral Response of DA17 1092
Historical Archaeological Assessment DA17 1092 Wallacia Memorial Park Cemetery at 13 Park Road and
Initial Environmental Waterways Referral Response of DA17 1092
Internal Plans DA17 1092 Wallacia Memorial Park Cemetery at 13 Park Road and 512 Mulgoa
Landscape and Visual Impact Assessment DA17 1092 Wallacia Memorial Park Cemetery
Landscape Design DA17 1092 Wallacia Memorial Park Cemetery
Landscape Drawings DA17 1092 Wallacia Memorial Park Cemetery at 13 Park Road and 512 Mulgoa
Landscape Specification Planting Works DA17 1092 Wallacia Memorial Park Cemetery
Owners consent DA17 1092 Wallacia Memorial Park Cemetery
Plan of Management DA17 1092 Wallacia Memorial Park Cemetery
Referral Response Senior Engineer Major Developments DA17_1092
Referral Response Senior Engineer Major Developments _ DA17_1092
RMS Response April 2018
RMS Response June 2018
Second Waste Services Referral Response of DA17 1092
Site Survey Plans DA17 1092 Wallacia Memorial Park Cemetery at 13 Park Road and 512 Mulgoa
Statement of Environmental Effects SOEE DA17 1092 Wallacia Memorial Park Cemetery at 13 Park
Strategic Demographic Assessment DA17 1092 Wallacia Memorial Park Cemetery
Sydney Water Response
Traffic Engineer 1ST Referral Response DA17 1092
Traffic Engineer Referral Response of DA17 1092
Traffic Impact Assessment DA17 1092 Wallacia Memorial Park Cemetery
Tree Assessment DA17 1092 Wallacia Memorial Park Cemetery
Version 1 Environmental Environmental Management Referral Response of DA17 1092
Waste Management Plan DA17 1092 Wallacia Memorial Park Cemetery
Waste Management Plan Operational DA17 1092 Wallacia Memorial Park Cemetery
Waste Services Referral Response of DA17 1092
Watercourse Assessment DA17 1092 Wallacia Memorial Park Cemetery
Appendix B CMCT Letter Requesting Amendment to the DA 26 Sep 2018
Appendix E Additional Groundwater Information 6 September 2018
Appendix F Sydney Water Correspondence 5 July 2018
Appendix G Park Road Wallacia Response to Orchid Sighting
Appendix H Department of Industry Water Correspondence 2018 11 08
Appendix I RMS Correspondence 15 June 2018
Appendix J Wallacia Memorial Park
Assessment Report
Assessment Summary v2
Internal Advice Reports
Referral Letter
Wallacia Memorial Park Civil Plans October 2018
Wallacia Memorial Park Landscape Plans October 2018
IPC_Conflicts Register
Adam Farrugia
Adam Farrugia_Redacted
Alan Hawkesley
Australian Devotees of Our Lady Penafrancia
Blessed Funerals
Colleen Hunter
Darrell Bell
Darrell Bell Speaker
David Marsh Speaker
Debra Jeffree
Edward McGovern Speaker
Elizabeth Barnes
Elizabeth French
Elizabeth French_Redacted
Enclosure Water servicing
Enclosure 1 Site Suitability and Criteria prepared by Urbis_Redacted
Enclosure 2 Letter Red Earth Geosciences
Enclosure 3 GRC Hydro Flood Study_Redacted
Enclosure 5 Wallacia Timeline of events
Enclosure 6 Park Road Wallacia Response to Orchid Sighting_Redacted
Frank Xerri
Gary Lynne Schuback
Glen Ilic
Gloria Stevenson
Graeme Buckett
Heather Davies
Jake Jeffree
Jake Jeffree_Redacted
James Murray Speaker
Jane Tickner
Jane Tickner_Redacted
Jane Tickner_Redacted
Jeff Agius
Jim Mueller
Joe March Speaker
JoEllen Thorpe Speaker
Julie Terry Jones
Julie Terry JonesRedacted
JulieAnne McGovern
Justine Louis
Justine Louis Speaker
Kara Jeffree
Kara Jeffree_Redacted
Ken Samuels Speaker
Les Rhodes
Les Rhodes_Redacted
Lisa Harrold
Louise Melissa Pulo
Majid Al Mabaraki
Majid AlMubarki Speaker
Margaret Stepniewski Speaker
Marguerite Hillsley
Matthew Fowler
Melissa Pulo
Michael Inzitari
Miguela Macatangay
Muslim Cemeteries Board
Name redacted
Name redacted_ Additional Information
Name redacted_speaker
Penrith Valley Chambers of Commerce
R Cafe
RA E McGovern
Response to IPC Public Meeting and Council Meeting_Redacted
Richard Lilian Vella
Richard Stepniewski
Richard Stepniewski_Redacted
Ruth Murdoch
Sandy Benton
Steve Hackett
Stratos Lawyers
Sue Corcoran
Sydney City Council_Redacted
Sydney City Council_Redacted
Tanya Davies
Tanya Davies Speaker
Tanya Davies speech
Teresa Alan Kingett
Teresa Nassif
Teresa Nassif_Redacted
Terry Light
Terry Read
Timothy Zachara
Tracey Haddad
Vicki Cullen
VIDEOS FROM WALLACIA A08418_Redacted
Wallacia P C and WPS SRC
Wallacia Progress Association
Wendy Thompson
WPA
WPA Speaker

Meetings

Date and time
8:00 PM Wed 27 March 2019
Venue
Wallacia Hotel
1590 Mulgoa Road, Wallacia NSW 2745
Contact
Philippa Vale 02 9383 2115

The meeting will be open to the public to observe the proceedings; however, if you would like to apply to speak at the meeting you must register before 5 pm on Wednesday 20 March 2019, by:

Completing the Registration Form  and emailing it to ipcn@ipcn.nsw.gov.au. We will then notify you if your request to speak has been accepted.  

Because we know some people find public speaking trying, and there will be others who cannot attend on the day, we will accept written comments up to one week after the public meeting. Written comments are weighed the same as spoken presentations.

For further details, please see the Notice for the Public meeting.

This public meeting will be recorded, and a written transcript published on our website. Speakers should familiarise themselves with the Commission’s ‘Public Meeting Guidelines’ prior to presenting to the Panel. 

The Commission reserves the right to cancel or postpone a public meeting without prior notice at its discretion, including on the advertised day of the public hearing. Where a public meeting is postponed or cancelled, the Commission will publish a statement to this effect on its website as soon as is reasonably practicable after the decision to postpone or cancel the public meeting has been made

If you have any questions about the public meeting process or Commission's role with the project, please contact the officer assisting the Commission, Diana Mitchell, on (02) 9383 2100.

 

Date and time

Anyone wishing to access the transcript of this meeting must read and agree to the following disclaimer:

This recording is made publicly available. Any views expressed by persons who presented to the Commission at this meeting, are not the views of the Commission or any of its employees.

To confirm that you have read the disclaimer and to view the transcript click here.

Date and time

Anyone wishing to access the transcript of this meeting must read and agree to the following disclaimer:

This recording is made publicly available. Any views expressed by persons who presented to the Commission at this meeting, are not the views of the Commission or any of its employees.

To confirm that you have read the disclaimer and to view the transcript click here.

Date and time

Anyone wishing to access the transcript of this meeting must read and agree to the following disclaimer:

This recording is made publicly available. Any views expressed by persons who presented to the Commission at this meeting, are not the views of the Commission or any of its employees.

To confirm that you have read the disclaimer and to view the transcript click here.

Date and time

Anyone wishing to access the transcript of this meeting must read and agree to the following disclaimer:

This recording is made publicly available. Any views expressed by persons who presented to the Commission at this meeting, are not the views of the Commission or any of its employees.

To confirm that you have read the disclaimer and to view the transcript click here.

Date and time

Anyone wishing to access the transcript of this meeting must read and agree to the following disclaimer:

This recording is made publicly available. Any views expressed by persons who presented to the Commission at this meeting, are not the views of the Commission or any of its employees.

To confirm that you have read the disclaimer and to view the transcript click here.

Date and time

Anyone wishing to access the transcript of this meeting must read and agree to the following disclaimer:

This recording is made publicly available, as required by, and in accordance with clause 25 of Schedule 2 of the Environmental Planning and Assessment Act.  Any views expressed by persons who presented to the Commission at this meeting, are not the views of the Commission or any of its employees.

To confirm that you have read the disclaimer and to view the transcript click here

Please note that certain sections of this transcript has been redacted as they may contain statement which are defamatory or offensive. A copy of the full transcript may be available upon request. Please contact us to request a copy on ipcn@ipcn.nsw.gov.au

Public Submissions

Make a Submission

We recognise the importance of community participation in our decision-making process. Using our ‘Make a submission’ form is the easiest way for you to make a submission on cases currently before the Commission.